Remodeling Contract
What Yours Should Include
Your Florida remodeling contract should lay out the complete scope, backed by drawings and a selections list, along with the price, a payment schedule linked to finished work, the way change orders are priced and approved, the timeline, who pulls the permits, the warranties and the method for resolving disputes. Florida also requires residential construction contracts over a modest dollar threshold to carry the construction lien law disclosure plus notice of the Homeowners' Construction Recovery Fund. Pay close attention to allowances: a low number packed with allowances isn't truly a fixed price.

What Belongs in a Remodeling Contract?
Everything rests on the scope. The contract should point to specific drawings and a selections list identifying each cabinet, countertop, tile, fixture and appliance by its model number or a clearly stated allowance, and it should list exclusions such as moving furniture, painting other rooms or structural repairs nobody could foresee. The price should be written out clearly, with each payment tied to a milestone, such as passing rough-in inspection, finishing cabinet installation or reaching final completion, instead of calendar dates. Florida requires that the contractor's license number appear on the contract, which should also say who is pulling the permits.
The remaining sections deal with what happens when the plan changes. The change order clause should call for written, signed changes showing the price and schedule impact before anyone does the work. The schedule should give a start window and a duration and explain what happens when weather, late materials or inspections slow things down. Check for a workmanship warranty and how manufacturer warranties are passed on to you, proof of insurance, cleanup and job-site rules, and a process for disputes. Collecting lien releases from subcontractors and suppliers belongs inside the payment process, not tacked on at the end.
| Section | What to look for |
|---|---|
| Scope and drawings | Plans referenced, a selections list and exclusions |
| Price and allowances | Fixed price, with realistic, clearly labeled allowances |
| Payment schedule | Draws linked to finished milestones and inspections |
| Change orders | In writing, signed and priced before work continues |
| Schedule | Start window, duration and how delays are handled |
| Permits and license | Who pulls permits; license number shown on the contract |
| Lien protection | Required lien law notice and releases with every payment |
| Warranty and insurance | Workmanship terms, manufacturer warranties and certificates |
Learn how our GC team manages permits, lien paperwork and a single fixed-price contract on every project.
What Does Florida Law Add to the Contract?
Under Florida's construction lien law, unpaid subcontractors and suppliers can put a lien on your home even when you have paid your contractor everything owed. That explains the lien law disclosure in the contract, the Notice of Commencement recorded with the Collier or Lee County clerk ahead of the first inspection on bigger jobs, and the need to gather lien releases as each payment is made. Deposits are regulated as well: when a contractor collects more than 10 percent in advance, permits must be applied for within 30 days and work must begin within 90 days after the permit is issued.
A few local clauses are worth adding. Hurricane season can stop work and hold up materials, so the contract should say how storm delays and site protection will be managed. Condo jobs need a contingency for association approval and a certificate of insurance that names the association. Seasonal owners who approve selections and change orders while living out of state should make sure the contract permits electronic signatures and states who may approve changes for them.

Remodeling Contract Before &
Remodeling Contract Questions
Should your remodeling contract be fixed price?
In most cases, yes. When the fixed price is based on finished drawings and selections, the contractor carries the risk of estimating mistakes. Review the allowances closely, since allowances set too low for cabinets, tile or fixtures can push a fixed price up later on. Conditions nobody could foresee should go through a defined change order process.
In Florida, how much of a deposit should a contractor request?
There is no single cap in Florida, but larger deposits do come with protections: a contractor collecting over 10 percent of the price in advance has to file for permits within 30 days and get work started within 90 days of the permit being issued, unless you agree to something else in writing. Link later payments to finished work.
What is a Notice of Commencement?
It's a document filed with the county clerk before work starts on larger projects, naming the owner, the contractor, the property and any lender. Under Florida law it establishes the framework for lien rights, and the building department usually wants a recorded copy before the first inspection. In most cases your contractor prepares it and you sign it.
Schedule a free consultation and we'll take you through our fixed-price contract one line at a time.
More in General Contractor
Why Clear Contracts Come From Cutting Edge
Cutting Edge Kitchen & Bath holds a Florida general contractor license and serves Naples and Marco Island, with a 4,000-square-foot Bonita Springs showroom at 28280 Old 41 Road, 500+ remodels around Southwest Florida and nine Best of Houzz awards. We write the contract after the design is done, not ahead of it: a no-cost LiDAR scan and photo-real 3D rendering lock in what is being built and with which materials, so the number we quote next is fixed. Permits, the Notice of Commencement and all lien paperwork are handled by us, and our in-house crews do the building, which leaves one company accountable from the signature to the final inspection.