On a Marco canal lot, the water side of the property is permitted apart from the house. A seawall goes through the City of Marco Island's seawall application, while docks and boat lifts use the City's marine application, and a dock that has to reach farther than the normal limits needs a boat docking facility extension decided by the Planning Board. A kitchen or bathroom remodel is a separate building permit again. Owners often have seawall, dock or lift work lined up in the same season as the interior job, and the two crews end up sharing the driveway, the side yard and the inspection calendar. This page lays out what each water-side permit asks for and how we schedule the interior work around it.

Seawall Permits & Your Bathroom Remodel
The City's seawall application starts with a scaled site plan that places the wall and gives its distance to each side property line, plus a survey or plat map with your lot marked that shows the width of the lot and the waterway. The survey has to locate the new or repaired wall against the neighboring seawalls and the platted boundary or mean high water line, and it must give the wall's height in NAVD 88. The package also includes a Design Professional Inspected Permit pre-permit affidavit. City staff inspect the existing conditions on site before the permit is issued, and the Engineer of Record must certify that the work followed the approved plans before a Certificate of Completion can be issued.
Owner and contractor affidavits are both notarized, a Notice of Commencement has to be recorded and posted at the job before the first inspection, and the form warns that starting without a permit quadruples the fee. If the marine contractor stages materials or pours on a vacant lot, a staging form goes to Community Affairs and a Temporary Use Permit is required under Ordinance 13-03. Dock, lift, electrical and plumbing work each need their own permits as well. For your bathroom, the main effect is timing: we sequence deliveries, dumpsters and tile work so they are not fighting a seawall crew for the same access, and we keep the interior permit and its inspections on a separate track.
Bathroom remodels on Marco canal homes are priced from $27,000 per bath.
Sort out the water-side schedule, then price the interior: the Marco Island Canal Homes bathroom builder gives you a starting figure.
Seawall Permits & Your Kitchen Remodel
Docks and boat lifts are filed on the marine application. It calls for an electronic plan set, a scaled survey or site plan showing the structure with its side setbacks and protrusion, and a survey or plat that gives the waterway width at your lot. Copies of any permits from other agencies are attached; the form has spaces for the Florida DEP and the Army Corps, and written state or federal approval has to reach the City before the dock permit is issued. A framing inspection follows, unsupported framing cannot be spliced without signed and sealed engineering, and a final survey must be approved before the Certificate of Completion. Lift power and dock lighting go to a licensed electrical subcontractor, hose bibbs to a licensed plumber, and the form reminds owners to check deed restrictions with the property owners association.
A dock that needs to reach past the normal limits goes through a boat docking facility extension petition. City staff review it against the criteria in Ordinance 03-15 and recommend approval or denial, and the Planning Board decides. The criteria ask whether the dock and moored boat would protrude more than 25 percent of the navigable waterway's width, whether at least 50 percent of the width stays open, whether the water is deep enough, using 4 feet below mean low water as a general guide, and whether seagrasses lie within 200 feet. An affected neighbor can appeal within 14 days of approval, and a building permit is still needed afterward. When that process runs long, we plan the kitchen so the interior work does not wait on it.
Kitchen remodels on Marco canal homes are priced from $42,000.

Plan the layout and finishes in the Marco Island Canal Homes kitchen builder and get a starting price while the dock paperwork moves.
More in Marco Island Canal Homes
Why Marco Canal Owners Choose Cutting Edge
Cutting Edge Kitchen & Bath is a design-build kitchen and bathroom remodeler, not a marine contractor. We work out of our Naples office for Naples and Marco Island, and our 4,000-square-foot showroom is at 28280 Old 41 Road in Bonita Springs. With more than 500 Southwest Florida remodels and nine Best of Houzz awards, we pull and close the interior permit, prepare its drawings and affidavits, and build the schedule around your seawall or dock contractor. A free LiDAR scan feeds the 3D render and the plans, one fixed-price contract covers the job, and our own crews do the work.