In a twenty-two-story tower above Clam Bay, our team is carrying one St. Nicole residence through a complete home remodel — kitchen, baths, floors, paint, and every finish surface — under a single schedule and a single fixed contract. There was no storm and no insurance claim behind it. The owner decided the interior was ready for a full reset. Watch it come together room by room.

9 YrsBest of Houzz
4.9★Verified Client Reviews
500+Projects Delivered
FixedPrice Set Upfront

No Storm Behind It.
Just a Choice.

Across Southwest Florida, most of the rebuilding over the past three years began with a hurricane. Not this project. The residence at 5550 Heron Point Dr was sound, comfortable, and fully livable — its owner looked at a 1991 interior and decided to replace all of it in one go instead of chipping away one room at a time over five years.

Choosing the work, rather than being forced into it, changes the whole job. No adjuster dictates the scope and no claim deadline sets the calendar. Kitchen, baths, floors, paint, doors, trim, and fixtures are planned together as one remodel with one price — less expensive and quicker than five separate projects, and the home comes back as one consistent design rather than ten years of decisions stacked on top of each other.

In ProgressSt. Nicole and Cutting Edge Progress
In ProgressSt. Nicole and Cutting Edge Tiling
In ProgressSt. Nicole and Cutting Edge Structure
In ProgressSt. Nicole and Cutting Edge Structure
In ProgressSt. Nicole and Cutting Edge Structure
In ProgressSt. Nicole and Cutting Edge Progress
In ProgressSt. Nicole and Cutting Edge Channel Floor
The Building

A 1991 Tower in Pelican Bay.
The Interior Is What Changes.

1991
Year Built
22
Stories
97
Residences
1,263–3,327
Square-Foot Plans

At the south end of Pelican Bay, St. Nicole backs onto the nature preserve and looks out across Clam Bay to the Gulf. The tower was completed in 1991 and has 97 residences, with plans from about 1,263 to 3,327 square feet; every unit has a covered parking space and terraces lined up toward the water. Inside the building you have two guest suites, an on-site manager, a pool and spa, a fitness room, and billiards, card, and social rooms. Beyond it sit the Pelican Bay amenities — the tram to the private beach, two beachfront restaurants, tennis, and the wellness center — with Waterside Shops and Artis-Naples close enough to walk to.

The timing is good. The association is wrapping up a designer renovation of the building — facade, lobby, pool and spa, fitness room, and social rooms — so a unit remodeled now finishes in step with a refreshed building instead of trailing it. Buyers have taken note: unit #1604 sold furnished for $1,700,000 in late 2025, about $201,000 over its list price. In a 1991 Pelican Bay tower, the address, the view, and the amenities are set. What happens inside the unit is still up to the owner.

The Scope

Wall to Wall —
Floor to Ceiling.

The kitchen is rebuilt from the slab up, with cabinetry staged at our 4,000 SF Bonita Springs warehouse, stone countertops, and new appliances. The baths become full wet rooms: tiled walk-in showers, new vanities, and complete waterproofing behind every wall. New flooring runs through the whole residence, specified for a high-rise on the Gulf and laid tight over a prepared slab.

Every surface is repainted, doors and trim are replaced, and fixtures and lighting are updated room by room, followed by the punch list that turns a job site back into a finished home. A high-rise adds its own steps: elevator bookings, association work hours, protected common areas, and materials staged in order so the unit is never waiting on a back-order. The photos above are refreshed as each room wraps up.

Phase by Phase

Eleven Steps.
A Full Remodel.

A full home remodel is really a chain of smaller jobs, and getting the order right matters more than any one trade. This is the real sequence at St. Nicole, with photos added as each step is completed.

Phase 01

Demo

First, everything that isn’t staying is removed — cabinets, counters, fixtures, floors, and finishes, all the way to the substrate. In a high-rise, this step shows whether a contractor really understands condo work: floors and shared hallways are protected, the elevator is booked and padded, and debris leaves on a schedule the association approved ahead of time, not whenever a truck happens to be free.

Demo is also when the building shows what is really there. With the walls open, the original 1991 construction can be seen for the first time — plumbing runs, wiring, and framing that no set of drawings captures completely. Before any new material is ordered, we photograph and re-measure everything, because scopes based on guesses are where change orders start.

St. Nicole and Cutting Edge Demo
St. Nicole and Cutting Edge Demo
St. Nicole and Cutting Edge Demo
St. Nicole and Cutting Edge Demo
Phase 02

Cutting Floor Channels

Relocating a kitchen or rearranging a bathroom means relocating drains, and in a concrete tower those waste lines run inside the slab. Crews cut channels into the slab along the new paths — exact, dusty, noisy work that must be done during the association’s allowed hours, with dust containment set up.

This step determines whether a new layout can actually happen. The post-tension cables and rebar in the slab limit how deep a cut can go, so every route is scanned and mapped before a blade meets concrete. A mistake here in a 22-story tower is a structural problem, not a cosmetic one, which is why this work is done early, supervised, and never made up on the spot.

St. Nicole and Cutting Edge Channel Floor
St. Nicole and Cutting Edge Channel Floor
St. Nicole and Cutting Edge Channel Floor
St. Nicole and Cutting Edge Channel Floor
Phase 03

Structure

Framing goes in for the new layout — moved partitions, reworked openings, soffits, and the backing that cabinets, vanities, and grab bars will need later. Each wall in a condo is structural, demising, or neither, and only walls in that last group can move freely. We confirm which is which against the building’s drawings instead of guessing.

This is also the step where finish quality is won or lost. Walls are set plumb and square now so tile fits tight later, ceilings are framed to one even plane so custom details have a true surface to attach to, and blocking is added wherever a fixture will hang. Skip this, and every trade that follows pays for it.

St. Nicole and Cutting Edge Structure
St. Nicole and Cutting Edge Structure
St. Nicole and Cutting Edge Structure
St. Nicole and Cutting Edge Structure
Phase 04

Plumbing

Supply and drain lines are run to every new fixture location — the kitchen sink, dishwasher, refrigerator line, and each bath fixture — and pressure-tested before anything is closed in. In a 1991 building, this is usually when original galvanized or early supply lines are swapped for modern pipe, since the walls are already open and the added cost is close to nothing.

Shower valves, tub fillers, and drain heights are set to the finished floor and tile depth, not the bare slab, so final surfaces land exactly where the drawings show. Water shut-offs are arranged with the association, because in a stacked tower a riser shutdown affects the neighbors — so it is scheduled and announced, never sprung on the building.

St. Nicole and Cutting Edge Plumbing
St. Nicole and Cutting Edge Plumbing
St. Nicole and Cutting Edge Plumbing
St. Nicole and Cutting Edge Plumbing
Phase 05

Electric

New circuits, boxes, and device locations are laid out for how the home will really be lived in — island outlets, under-cabinet lights, appliance circuits, GFCI protection in the baths, and lighting split into zones instead of one switch per room. A 1991 unit was wired for the appliance loads of 1991, so panel capacity is checked before the scope is final.

Lighting gets designed now rather than picked at the end. Recessed layouts, cove and toe-kick lighting, and dimming zones all rely on rough-in locations that are locked in once the drywall goes up. We place them against the furniture plan and the ceiling design so light falls where people stand, sit, cook, and read.

St. Nicole and Cutting Edge Electric
St. Nicole and Cutting Edge Electric
St. Nicole and Cutting Edge Electric
St. Nicole and Cutting Edge Electric
Phase 06

HVAC

Ductwork is reworked for the new floor plan, supply and return vents are moved, and the air handler and condensate lines are updated to today’s standard. In Southwest Florida this goes beyond comfort — controlling humidity is what protects cabinets, floors, and finishes in a Gulf-front home that sits closed up for part of the year.

Vents and returns are placed to work with the ceiling design, not against it, which is why HVAC and the custom ceiling are planned together rather than one being squeezed around the other later. Condensate lines are sloped and fastened correctly, because in a stacked building a slow leak never stays in one unit.

St. Nicole and Cutting Edge HVAC
St. Nicole and Cutting Edge HVAC
St. Nicole and Cutting Edge HVAC
St. Nicole and Cutting Edge HVAC
Phase 07

Tiling

Waterproofing comes before tile — a complete membrane system behind and under every tiled surface, with corners, curbs, and penetrations finished by hand. Tile is what you see, but waterproofing decides whether the bathroom still holds up in fifteen years, and it disappears from view the moment tile goes over it.

Each layout is dry-fit and centered before anything is set, so cuts land where they are least noticeable and pattern lines run cleanly from floor to wall to niche. Large-format tile and stone need a flat base and the correct setting material, and we confirm both ahead of time instead of finding out halfway through.

St. Nicole and Cutting Edge Tiling
St. Nicole and Cutting Edge Tiling
St. Nicole and Cutting Edge Tiling
St. Nicole and Cutting Edge Tiling
Phase 08

Flooring

Before any plank or tile goes down, the slab is prepped and leveled — the channels cut in phase two are filled and floated flat again, and flatness is measured against the tolerance the flooring maker actually specifies. Most flooring problems start with the substrate, not the product.

Condo floors have one requirement houses don’t: acoustic underlayment that meets the association’s sound-transmission standard, a condition of approval in most Pelican Bay high-rises. Material acclimates inside the unit before it is installed, and transitions between rooms are planned so the floor reads as one continuous surface.

St. Nicole and Cutting Edge Flooring
St. Nicole and Cutting Edge Flooring
St. Nicole and Cutting Edge Flooring
St. Nicole and Cutting Edge Flooring
Phase 09

Custom Ceiling

The ceiling is the biggest unbroken surface in the home, and the one most often left as plain flat drywall. Here it is part of the design — coffers, trays, cove details, and dropped planes that mark out the living and dining areas and give the recessed and cove lighting a deliberate place to live.

Think of it as millwork overhead. That is why the ceiling is framed back in phase three and coordinated with HVAC and electric before either is roughed in: every duct, vent, sprinkler head, and light has to fall inside the finished shape instead of being cut through it later.

St. Nicole and Cutting Edge Setting Cabinets
St. Nicole and Cutting Edge Setting Cabinets
St. Nicole and Cutting Edge Setting Cabinets
St. Nicole and Cutting Edge Setting Cabinets
Phase 10

Cabinets

Kitchen and bath cabinets are staged at our 4,000 SF Bonita Springs warehouse, so every box is checked locally instead of showing up from a distributor the same week it is needed. Runs are leveled and shimmed to the wall rather than the floor, so doors line up and drawers slide just as smoothly in year five as in week one.

Countertops are templated only once cabinets are set and secured — never earlier — so the stone is cut to the room as it was actually built, not to a drawing. Hardware, panels, and integrated appliance fronts follow, and the room stops looking like a job site and starts matching the renderings.

St. Nicole and Cutting Edge Setting Cabinets
St. Nicole and Cutting Edge Setting Cabinets
St. Nicole and Cutting Edge Setting Cabinets
St. Nicole and Cutting Edge Setting Cabinets
Phase 11

Progress Shots

Paint, doors, trim, fixtures, and the punch list — the small finishing work that turns a completed build into a home. We walk every surface, adjust every door, test every switch and fixture, and fix anything that isn’t right before we call it finished.

This section grows as the home comes together. If you are thinking about the same project in your own St. Nicole unit or elsewhere in Pelican Bay, these are the photos to study — a real job at a real Naples address, not a showroom, nearing the finish.

St. Nicole and Cutting Edge Progress
St. Nicole and Cutting Edge Progress
St. Nicole and Cutting Edge Progress
St. Nicole and Cutting Edge Progress
St. Nicole Project FAQ

Questions We Hear Most.

Why remodel the entire home at once rather than one room at a time?
Lower cost and a consistent result. Handling kitchen, baths, floors, and paint as one job means a single mobilization, one round of protection and elevator bookings, one association approval, and one crew sequence — instead of paying those overhead costs five times over. It also means the finished home looks like one design, not ten years of choices that never quite matched.
How long will a complete condo remodel take?
Standard scopes take 4–8 weeks, and larger or fully custom projects take 8–12 weeks. In a Pelican Bay tower we stage and sequence materials around the association’s calendar so the unit is never idle, and the schedule is written into your contract rather than given as a guess.
Will you take care of the condo association requirements?
Yes. Board approval packages, insurance certificates, elevator bookings, approved work hours, common-area protection, and debris plans are all part of our job. It is the same process we follow on twelve units at Eden House on Fort Myers Beach and at The Sandcastle on Marco Island.
Can the remodel be done before season?
Usually that is exactly what the schedule is built for. We plan the scope backward from your target date, and since the contract is fixed-price with the timeline written in, the finish date is a commitment, not a hope.

Want Your Home
Done Next?

Complete home remodels across Pelican Bay, Naples, Marco Island, and the rest of Southwest Florida — one crew, one timeline, one fixed contract.

📞 (239) 237-7000 Book Free Consult →
10 AI Tools · Free After Consultation

Your Naples & Marco Island
Remodel Tools.

AI room previews, neighborhood comp data and Naples market numbers, made for homeowners in Naples and on Marco Island. These tools charge $14–$36/month elsewhere. You get them free after your consultation.

01
AI Room Visualizer
Upload a photo. See your kitchen or bath transformed in 30 seconds in any style, any material.
Photo → AI Render
02
Naples Style Matchmaker
6 questions. A personalized design profile with AI renders at every price tier.
Style Profile
03
InvisaCook Visualizer
See any kitchen without a visible cooktop. Authorized exclusive dealer — the only tool of its kind.
Exclusive to South Florida
04
Cabinet Visualizer
Swap door styles, finishes, and paint colors from our actual showroom catalog onto your kitchen.
Product Visualization
05
Countertop Visualizer
See Cambria, Dekton, quartzite, and marble options applied directly to your kitchen photo.
Material Selection
06
Paint Color Visualizer
Repaint any room in seconds — every wall, any color, photo-real light and shadow.
Color Selection
07
Flooring Visualizer
Swap tile, LVP, and wood floors into your rooms — laid in the right direction, at the right scale.
Material Selection
08
Bathroom Visualizer
Tub-to-shower conversions and full bath restyles rendered on your actual bathroom photo.
Photo → AI Render
09
Outdoor Kitchen Visualizer
Turn your lanai photo into a full outdoor kitchen — grills, stone, bar seating, lighting.
Photo → AI Render
10
Bonus Room Converter
Empty spare room in — office, gym, media room, or guest suite out. Four futures, one photo.
Room Conversion
Access all 10 tools — free with your consultation.
90-day access · 50 renders · Watermarked for sharing · No subscription
Unlocked after your
free planning session
Book Free Consult →